Petronas Rapid Project: Shipment to Malaysia of first two ARDS Reactors

During the last weeks it has been successfully completed the shipment of the first lot two ARDS Reactors from Porto Marghera, Venice (Italy), directed to Malaysia.

Petronas Rapid Project

The two ARDS Reactors, of a total approx. weight of. 1500 tons, have been completed at ATB Porto Marghera workshop and shall be part of the new Refinery and Petrochemical Integrated Development (RAPID) Project of PRC Refinery and Cracker SDN.BHD (Petronas/SEG).

ATB’s scope of supply includes four Reactors made by Vanadium Modified Material of 289 thickness, with process internals.

The remaining two Reactors are in completion and are expected to be shipped by few weeks.